The hotel is going to build more new villas and a new swimming pool from this September 2007 until 30 September 2008.
The hotel is going to build 14 luxurious Triple Pool Villas and new swimming pool.The construction will be taking place during 1 September 2007 to 30 September 2008.
Construction near by Sawasdee Village, Phuket The expansion more new 14 luxurious Triple Pool Villas and new swimming pool of Sawasdee Village ,Phuket which we are pleased to bring your kind attention for the update of construction
- Driving the foundation piles ? Already completed since 05 Oct,07 Room No. 1-4 (Include Mock up room)
- Build up structure Target of completion date 15 Nov,07
- Interior decoration Period 16 Nov ,07-15 Jan,08 .Target of completion date 15 Jan,08 Room No. 5-14
- 01 Oct 07– 31 May, 08 : Build up the structure of Room No.5-14 and the noise will occur from hammering or nailing only; however, this area is away from the assigned rooms for In house guest so they will not effected with any noise Working hour of construction will be during 10.00 am -19.00 pm
- 01 Jun- 14 Sep, 08 : Process of Interior decoration and most of the materials will be produced outside the site and will be built in the room later on so none of the noise will be annoyed In house guests during that time.
- 15 Sep-20 Sep,08 : Complete of project and Operation will clean up all area.
- 20-30 Sep,08 : Trial run period in order to ensure in the completion of
• Interior decoration : Most of the materials will be produced outside the site and will be built in the room later on so none of the noise will be annoyed in house guests during that time. ? Period 16 Nov ,07-15 Jan,08 .Target of completion date 15 Jan,08
• Working hour of construction will be during 10.00 am -19.00 pm
01 Oct 07– 31 May, 08 : Build up the structure of Room No.5-14 and the noise will occur from hammering or nailing only; however, this area is away from the assigned rooms for In house guest so they will not effected with any noise Working hour of construction will be during 10.00 am -19.00 pm
01 Jun- 14 Sep, 08 : Process of Interior decoration and most of the materials will be produced outside the site and will be built in the room later on so none of the noise will be annoyed In house guests during that time.
15 Sep-20 Sep,08 : Complete of project and Operation will clean up all area.
20-30 Sep,08 : Trial run period in order to ensure in the completion of project.
01 Oct,08 : All rooms and facilities is ready to welcome all guests arrival